PROJECT UPDATES
This page is reserved for sharing information on project goals, time lines, schedules, and milestones.
The current project schedule is:
- Week of 11/24/08: Waterline work crossing Woodinville - Duvall Road and utility work continuing from Stella south.
- Week of 11/17/08: Waterline work in Stephens Street west of Main. Vault installation near library and utility work from Stella to Stewart.
- Week of 11/10/08: Waterline work on Stella Street, utility work continues between Stewart and Stella. Sawcutting may begin in Main Street at different areas of the project.
- Week of 11/3/08: Waterline and utility work on Cherry Street. Sidewalk removal may begin south of Cherry Street.
- Week of 10/27/08: Waterline installation will continue through Stephens Street. Utility trench work will also begin at Stewart Street behind waterline work.
- Week of 10/20/08: Waterline installation begins from Stewart to Stella Street.
- Week of 10/13/08: Asphalt grinding in water trench on west side will begin from Bird St to Stephens St.
- October 13, 2008: Construction Start Date
- September 25, 2008: Award Apparent Low Bidder
- September 12, 2008: Scheduled Bid Opening
- August 21, 2008: Bid Announcement Date