Recent / Upcoming Activity
- Week of 7/12/2010: Finish water line, continue irrigation and site grading.
- Week of 7/5/2010: Continue sidewalk installation and begin irrigation. Continue waterline work from 145th to end of project.
- 7/6/2010: 9 AM - 6 PM: Water main tie-ins at Miller and Comegys. See Map and Notice for more information.
- 7/5/2010: No Work.
- Week of 6/28/2010: Finish rockery and begin sidewalk installation. Waterline installation continues between 145th and Kennedy.
- Week of 6/21/2010: Water main installation continues south of Kennedy. Rockery and sidewalk grading north of Taylor Street.
- 6/17/2010: Water main tie-ins. See NOTICE for more information. Click HERE for a map showing affected areas. 3:15 PM: Water Service back on to all locations north of Stephens. 4:00 PM: Resumption of normal water service north of Kennedy is anticipated at approximately 5 PM and resumption of normal water service south of Kennedy is anticipated at approximately 6 PM.
- Week of 6/14/2010: Rockery work continues south of Dorothy.
- Week of 6/7/2010: Water main installation south of Taylor Street. Detour route will be revised. Rockery installation begins from Ring to Dorothy.
- 6/4/2010: No Work Duvall Days
- Week of 5/31/2010: Crew installing water service taps. Valve cut-ins and service interruptions for some customers on June 2nd.
- 5/31/2010: No Work Memorial Day
- Week of 5/24/2010: Storm structures installed. Water main installed south of Dorothy north of Park.
- Week of 5/17/2010: Water main installation continues. Water main tie-in and service disruptions on May 19.
- Week of 5/10/2010: Install water main and excavate for rockery / path between Stephens and Dorothy Streets.
- Week of 5/3/2010: Site clearing, storm installation, and potholing.
- Week of 4/28/2010: Potholing in Stephens Street. Intersection will be flagged. Clearing continues.
- Week of 4/26/2010: Site clearing and tree removal begins from Ring Street to Taylor Street. Trench line is pulverized in place throughout the project limits.
|